Structural framing works completed for 3x double story dwelling, with detailed attention to alignment, floor levels, and framing layout to ensure consistency across the build.

The brief

A private client engaged us for the carpentry on a three double-storey townhouse development at Neimur Avenue, Deer Park. Three dwellings on the one block, so we handled the full run from ground-floor frame through to fix, and the work was staged across the units rather than all at once.

How we built it

We set out and completed the ground-floor framing before installing the Posi-Strut flooring, first-floor frames, and roof trusses. Render foam cladding was then installed across both levels, followed by eave sheets and window installation to complete the external shell. The same process was repeated across all three dwellings, with each stage inspected and signed off before progressing to the next.

Neimur Ave, Deer Park
The double-storey townhouses were successfully framed, clad with render foam, and brought to lock-up stage. Each dwelling was completed to inspection requirements, providing a weather-tight structure ready for the next phase of construction.

The outcome

Three frames up, clad and locked up, with the fix carpentry done. Inspections signed off stage by stage and each unit handed over clean.